Renovation of District Heating Pipelines – Svogerslev District Heating
Renovation of District Heating Pipelines – Svogerslev District Heating
- Role: Consultant
- Scope: 1,300 metres of main and distribution pipelines (DN32–DN80) and 1,700 metres of flexible service connections (AluPEX) supplying 90 customers
- Client: Svogerslev District Heating
- Status: Under construction
Strategic renovation of the pipeline network with focus on operation and maintenance
Norsyn provides technical consultancy services in connection with a comprehensive renovation of the district heating pipeline network in Svogerslev, focusing on operational reliability, ease of maintenance and reduction of future operating costs. The project includes the complete replacement of main pipelines, distribution pipelines and service connections and aims to establish a robust and future-proof pipeline network.
As a basis for the renovation strategy, Norsyn has carried out technical, hydraulic and financial analyses focusing on the condition, remaining service life and operational challenges of the existing network. The consultancy services include assessment of design principles and technical solutions, pipeline dimensioning, hydraulic analyses and preparation of a phased five-year implementation and maintenance plan.
Norsyn also assists with detailed design, preparation of tender documents and planning of the procurement process, as well as ongoing budget monitoring and financial management. The consultancy supports operational requirements through prioritisation of construction phases, coordination with the operating organisation and technical supervision during the implementation of the project.